![]() |
Newly Revised ASHRAE 90.1 Standard Addresses the Thermal Performance of Metal Building EnvelopesBy Chris P. Crall
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Table 1. |
|||
|
Assembly U-factors for Metal Building Roofs |
|||
|
Insulation System |
Nominal R-Value U-factor (*) |
Btu/(hr• ft2• °F) |
% Reduction from Uninsulated Case |
|
None |
0 |
1.28 |
- |
|
Screw Down Roof |
10 |
0.153 |
88.0 |
|
|
11 |
0.139 |
89.1 |
|
|
13 |
0.130 |
89.8 |
|
Standing Seam Roof With Thermal Blocks (Single Layer) |
|||
|
|
10 |
0.097 |
92.4 |
|
|
11 |
0.092 |
92.8 |
|
|
13 |
0.083 |
93.5 |
|
|
16 |
0.072 |
94.4 |
|
|
19 |
0.065 |
94.9 |
|
Standing Seam Roof With Thermal Blocks (Double Layer) |
|||
|
|
10/10 |
0.063 |
95.1 |
|
|
10/13 |
0.058 |
95.5 |
|
|
13/13 |
0.055 |
95.7 |
|
|
10/19 |
0.052 |
95.9 |
|
|
13/19 |
0.049 |
96.2 |
|
|
19/19 |
0.046 |
96.4 |
|
Filled Cavity with Thermal Blocks |
|||
|
|
19/10 |
0.041 |
96.8 |
(*) U-Values in Table 1 are taken from the ASHRAE Table A-2
As in any modeling effort, the results will vary depending on the assumptions. Key assumptions that apply to these results are listed below:
These assumptions were felt to apply to typical metal building roof constructions.
One key assumption is that NIA Certified faced insulation is used. The Certified Faced Standard is a standard product specification for flexible faced fiberglass metal building insulation. It was developed by the MBI Laminators Committee of the National Insulation Association and it covers the composition and physical properties of faced insulation intended for use in the walls and roofs of metal buildings. The standard requires that the thermal performance of the laminated insulation product meet the rated R-value out of package.
Table 1 includes a column that gives the percentage reduction in heat flow through the roof compared to the uninsulated case. As we know, insulation systems follow the law of diminishing returns. The first increment of insulation produces the largest return, with additional increments reducing heat flow further, but by smaller amounts. This is clearly shown in the table. Determining the "optimal" insulation level becomes an engineering economics problem, which attempts to balance the incremental installed cost with the incremental dollar savings generated over the life of the project. Standard 90.1 utilizes this approach in setting the U-factor criteria for the various climatic zones.
For screw down roofs (SDR), the compression of the insulation between the purlins and the roof sheet has a major impact on the thermal performance of the system. In addition, metal fasteners are a significant short circuit for heat transfer through the envelope. The FEA model properly accounts for these details. Even with these defects, reductions in heat flow of roughly 90% (compared to the uninsulated case) are possible.
For standing seam roofs (SSR), the U-factors are significantly better (lower) than for the SDR roof with the same nominal insulation value. This is primarily due to the inclusion of the 1"x3" thermal spacer block placed over the purlins where the insulation is compressed. The block is an effective fix for the thermal short circuit at the purlins. Thermally, the SSR with the thermal spacer block is a much more efficient system that should be considered in colder climates. Using double layers of insulation, U-factors down to 0.046 Btu/(hrft2°F) are achievable (a 96% reduction compared to the uninsulated baseline).
Finally, note the results for filled cavity insulation systems. For most metal buildings, the vapor retarder facing and the insulation layers are installed from the top of the roof prior to installation of the roof sheeting. This method leaves the purlins exposed to the indoor conditions below. Other installation approaches use banding to support the insulation from below the purlins. These systems can be used on new buildings, and may be adaptable to re-insulation work in existing buildings. The approach has the additional advantage of allowing the insulation to completely fill the cavity between purlins. While the thermal short circuit of the steel purlins is still present, its effect is reduced.
A typical "filled cavity" system was analyzed using the FEA approach. In this case, R-19 insulation (supported from below by banding attached to the bottom of the purlins) is installed to completely fill the cavity. R-10 insulation is installed over the purlins with a thermal block. This system has a U-factor of 0.041 Btu/(hrft2°F), which translates to a 97% reduction in heat transfer compared to the uninsulated case.
Table 2 summaries the FEA results for selected metal building walls installed in the conventional manner. These calculations assumed a girt spacing of 7 ft.
|
Table 2. |
||
|
Assembly U-factors for Metal Building Walls |
||
|
Nominal R-Value |
U-factor (*) Btu/(hr•ft2• °F) |
% Reduction from Uninsulated Case |
|
0 |
1.18 |
- |
|
10 |
0.134 |
88.6 |
|
11 |
0.123 |
89.6 |
|
13 |
0.113 |
90.4 |
|
(*) U-Values in Table 21 are taken from the ASHRAE Table A-9 |
||
As expected, the results are somewhat better than the U-factors for screw down roofs, reflecting primarily the wider girt spacing assumed.
The revised ASHRAE Standard 90.1-99, for the first time, treats metal building walls and roofs as distinct envelope elements. Maximum U-factor criteria are set based on life cycle economics. The NAIMA three-dimensional finite element model was used to estimate the thermal performance of typical metal building envelope elements taking into account compression of insulation at the purlins and girts as well as thermal shorts due to clips and fasteners. The resulting U-factors are published in Appendix A of the Standard and may be used to demonstrate compliance.
There are many metal building insulation systems available in the industry. Performance claims generally cannot be compared directly simply because of the various methods and assumptions made. FEA offers a cost-effective way of standardizing the evaluation, allowing contractors, architects or owners to make "apples to apples" comparisons. The cost of each system can then be evaluated to determine the real economic value of alternative systems.